Q: 1
The Internal Rate of Return is:
A. The Discount Rate which produces the highest NPV
B. The Discount Rate which produces the lowest NPV
C. The Discount Rate which matches the normal bank interest rate
D. The Discount Rate which produces a zero NPV
Answer: D
Q: 2
What is product based planning?
A. A technique that marketing departments use to launch new products and services.
B. A technique that seeks to identify tasks and activities
C. A technique that monitors the progress of the project
D. A technique that concentrates on the identification and definition of what the project is to deliver
Answer: D
Q: 3
Complete the following statement choosing the most appropriate option from those below. “The design authority is responsible for?”
A. Co-ordinating the overall programme and constituent projects
B. The programme
C. Business integrity within the programme
D. Technical integrity across projects
Answer: D
Q: 4
End Project Reviews should be used to:
A. Identify who was responsible for any failures
B. Consider support requirements
C. Capture lessons learned for future projects of a similar nature
D. Agree when the project team can be released for other work
Answer: C
Q: 5
Which of the following is NOT typically a component of a Project Initiation Document / Terms of Reference?
A. Detailed Analysis
B. Timescales
C. Risks
D. Objectives
Answer: A
Q: 6
Which level of plan forms the basis of the project manager’s day to day control?
A. Stage / Tranche
B. Individual
C. Project
D. Team
Answer: A
Q: 7
The primary objective of the configuration control process is to ensure that deliverables / products are:
A. Not changed once completed without approval
B. Logged at inception
C. Audited following changes
D. Given an unique ID
Answer: A
Q: 8
In a formal Quality Review who does NOT have an automatic right of attendance?
A. Administrator / Recorder
B. Qualified Reviewers
C. Deliverable producer or representative
D. Project Manager
Answer: D
Q: 9
Which of the following is NOT a formal Configuration Management process?
A. Control
B. Audits or Verification
C. Validation
D. Identification
Answer: C
Q: 10
The fact that a “today” is not worth the same as “ in the future results in the application of what to future monies?
A. Internal Rate of Return
B. Contingency
C. Inflation
D. Discount rate
Answer: D
Q: 11
“A typical plan at the business or strategy level will include the major deliverables to fulfill the strategy, the resource expenditure, a plan for the achievement of benefits, and” Which of the following completes this statement?
A. The programme reporting arrangements to be used
B. A description of the techniques used in the preparation of the plans
C. The plans of the portfolio projects
D. The major milestones or events
Answer: B
Q: 12
Click on the Exhibit button.
Click the Calculator button.

In Chart 1, at the Month 7 set of figures, what is the Schedule Variance? Is it:
A. -0
B. -20
C. -1 Month
D. +1 Month
Answer: A
Q: 13
The overall responsibility for monitoring and managing the project risk log should be taken by which role?
A. Project Manager
B. Risk Owner
C. Project Sponsor
D. Project Support Co-ordinator
Answer: A
Q: 14
The resolution of an Exception situation is the ultimate responsibility of:
A. The person who discovered the problem
B. The Users
C. The Project Sponsor/Board
D. The Project Manager
Answer: C
Q: 15
The business case is assessed:
A. Throughout the project
B. During feasibility
C. At major milestones
D. When major issues are encountered